browser icon
You are using an insecure version of your web browser. Please update your browser!
Using an outdated browser makes your computer unsafe. For a safer, faster, more enjoyable user experience, please update your browser today or try a newer browser.

Site Start

Boxing and Waffle Pods in place for Slab

I went past the block yesterday on my way home from work hoping to find everything ready for the Slab to be poured today. Unfortunately, there was little that had changed. So I gathered that he slab would not be poured today. When I went past after work today I found that all the boxing had been … Continue reading »

Categories: Site Start | Leave a comment

More leveling of the Site

Today, I went over to the block to get the footage off of the time-lapse camera and received a nice surprise. They have been there on Friday and spread crushed rock over the site and leveled it all out ready for the Slab to be poured. I spoke to the site supervisor yesterday and he … Continue reading »

Categories: Site Start | Leave a comment

Site Scrape and Leveling Done

On Thursday I was told that there were people at the block with Bob cats leveling off the site. I was unable to go past the site till after dark so wasn’t able to see much. I had to see what they had done, so I went past on my way to work this morning and … Continue reading »

Categories: Site Start | Leave a comment

Under Slab Pipe Work Done

After work today I went past the block to find that the under slab pipe work for the sewer connections has been done. Everything appears to be in the correct positions.

Categories: Site Start | Leave a comment

Action at the Block

Today, after work I went past the block and found the beginnings of where they will be marking out the site. I will be giving GJ Gardner a call tomorrow, as I have a time-lapse camera that I am hoping to set up at the back of the block to record the progress of my house … Continue reading »

Categories: Site Start | Leave a comment