Tiles and Driveway Started

Posted by on July 13, 2012

This week the tiler started his work. On Monday, he did the wet seal around the showers and bath and sorted out the tiles for all the different areas. I dropped in at lunchtime and had a quick look and took a couple of photos while I was there.

Shower Wet Seal

Shower Wet Seal

Bath Wet Seal

Bath Wet Seal

Throughout the week the tiler was there laying the tiles. He has done the laundry, kitchen, bathroom and ensuite floors. He has also started the shower walls. Below are some photos of the progress.

Dining Tiles

Dining Tiles

Bathroom Tiles

Bathroom Tiles

Shower Wall Tiles

Shower Wall Tiles

Laundry Tiles

Laundry Tiles

Ensuite Tiles (Through Window)

Ensuite Tiles (Through Window)

I spoke to the site supervisor today and he said that the driveway would be pegged out today ready to be excavated on monday and the driveway poured sometime next week. When I got there this afternoon I found that the driveway had already been dug out and had the sand base smoothed out ready to go. They have also prepared the spot for the slab under the hot water service. Below are some photos.

Driveway

Driveway

Entrance

Entrance

Driveway

Driveway

Hot Water Service Pad

Hot Water Service Pad

 