Monthly Archives: February 2012
Preliminary Drawings
Today, I received the Preliminary Drawings from GJ Gardner. I have picked up a few minor mistakes such as: The passage between the laundry and bathroom heading towards bedroom 2 and 3 is marked on the plan as tiles and it should be carpet. The exhaust fan for both the bathroom and ensuite are not … Continue reading
Initial Deposit – Paid
Today, I went into GJ Gardner and paid the initial deposit. By paying this deposit the following things can happen: Plans are drawn Soil Test and Site levels I was told that I should have the preliminary drawings for me to check through within two weeks. Once I have checked the preliminary plans for any mistakes I should then … Continue reading
Quote to add Alfresco
Toady, I received the quote back from GJ Gardner. The extra roof for the alfresco fits within my budget so at this stage I have added it in. The next step for me is to pay for a soil report and site levels for the block. Once I have paid for these things they become mine … Continue reading